The project entailed the design and construction of the underground gas storage faciltiy within Nuon's operational premises.
The project consisted of a two storey high compressor building, three caverns and two tie-ins.
The civil aspect of the project entailed constructing foundations for the gas lines, glycol unit and the construction of a control building. The extension of the existing Nuon facility involved a new compressor housing, consisting of a one storey (double height) construction, in which two compressor foundations were formed. We also installed all the associated machinery. Three additional caverns (underground stores) were created for the storage of a total of 80 million m3 of natural gas. The caverns are located at a depth of about 1200m. In addition, there were two other associated constructions.
Joint Venture Papendrecht VOF
For the civil aspects of the project we created a collaboration with Mainka Bau from Lingen, namely:
Arge Nuon Hochbau II